Completed Projects


A sample of our successfully completed projects include:

resurfacing-roaedit
2014 | Maintenence Management for major roads, Belait District

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $5.3M
Duration: 24 months

Scope of Works: Integrated maintenance management along major roads in Belait District. Works include traffic management, earthworks, milling of existing road, ground levelling, relaying K1 & asphalt, kerb reconstruction, drainage improvements and upgrading of line markings.

jalan maulana road
2014 | Resurfacing works on Jalan Maulana, Belait District

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $1.6M
Duration: 12 months

Scope of Works: Resurfacing of Main Roads, Jalan Maulana in the Belait district. The works included milling of the existing road, heavy deep lift patching, relaying asphalt and K1, kerb reconstruction and line marking of new works. All works are being completed under live vehicular traffic conditions with temporary traffic management performed.

drain-edit
2013 | Upgrading existing concrete drainage system, Belait District

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $1.5M
Duration: 18 months

Scope of Works: Upgrading of Existing Concrete Drainage System along Jalan Setia Diraja, Jalan Pandan Dua and Jalan Pandan Tiga, Belait District. Involved demolishing of existing drainage, construction of sewer using boring, temporary diversion of existing drainage to complete works and temporary traffic management.

mum-road-pic1edit
2013 | Augmentation of Jalan Singa Menteri, Belait District

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $9.0M

Scope of Works: Widening of Jalan Singa Menteri, Phase II. Works include earthworks, milling of existing road, relaying K1 and asphalt, kerb reconstruction, drainage reconstruction and line marking of new works.

distribution-road-edit
2013 | Upgrading and Rehabilitation of Distributor and Access Road, Belait District

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $1.5M
Duration: 12 months

Scope of Works: Upgrading and rehabilitation of distributer and access road around the Belait district which includes earthworks, relaying asphalt, concrete protection of existing services, repair of existing kerbs and upgrading line marking.

labi-sg-liang2resize
2012 | Upgrading Road at KM7, Jalan Labi, Belait District

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $2.1M
Duration: 12 months

Scope of Works: Upgrading road at KM7, Bukit Puan, Jalan Labi. Works included bulk earthworks, levelling pavement construction, concrete works, kerb construction, drainage construction and line marking.

2011 | Construction of Main Access Road, Auxiliary Road and Associated Drainage System, Sungai Paku

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $8.75M
Duration: 10 months

Scope of Works: The building of the main access road, auxiliary road and associated drainage system. Works include large scale earthworks, road construction, auxiliary road configuration, kerb construction, drainage and sewer manhole construction and building of an electrical substation.

seria-housing-edit
2007 | Seria Housing Scheme Phase 4 & 5 Earthworks

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $5.0M
Duration: 15 months

Scope of Works: Lorong Tengah Housing Scheme Phase 4a & 4b. Works involve large scale earthworks, external drainage works and common services trenching.

sg-liang-housing-edit
2007 | Kampung Lumut/Sungai Liang Resettlement Housing Scheme, Phase 5&7 Earthworks

Client: Public Works Dept. (JKR), Ministry of Development, Brunei
Awarded Value: $6.8M
Duration: 18 months

Scope of Works: Kampung Lumut/Sungai Liang Resettlement Housing Scheme, Phase 5&7. Works involve large scale earthworks, external drainage works and common services trenching.